The recent round of funding for National Bike Path Projects under the Nation Building Stimulus Plan could be used to arrive at a lower cost per kilometre. The grants are for half the cost of the project, thus in the table below the cost per meter is arrived at by doubling the grant amount before dividing it by the length of the path built. Some of these paths are in concrete, some in asphalt. The average cost per meter of these projects comes to $191 (25.91 km of paths built for $4.944 million)

Cost of Public shared paths (based on Infrastructure Australia Grants)
(Note: Grants are for 50% of total cost)
Grant $ Paths km Cost m
Nannup

90000

2.50

72

Geraldton

202000

4.08

99

Northam

133000

2.30

116

Belmont

29000

0.50

116

Kwinana

612000

8.21

149

Joondalup

120000

1.60

150

Merredin

88000

0.90

196

Joondalup

125000

1.00

250

Canning

775000

4.00

388

South Perth

298000

0.82

723

Note: Cost per km is Grant * 2 divided by length)